Tenant Information

Tenant Name: CHINA CONSTRUCTION SAUSUM
Office Number: 407
Area: 213.58 m²
Floor: 4

Bill Information

Calculated According to: Standard calculation
Issued By: ELEKTROPRIVREDA SRBIJE
Period: March 2026
Generated: Apr 03, 2026 15:29

Consumption & Rate Information

20.00
Granted Power (kW)
425.15
Total Spent (kWh)
14.15 RSD
kWh Price

Calculation Breakdown

Description Calculation Amount
Fee for stimulus of privileged consumers 425.15 kWh × 0.816 346.92 RSD
Access to the system for distribution of electricity/Granted power 20.00 kW × 121.79 2,435.80 RSD
Access to the system for distribution of electricity/Active 425.15 kWh × 1.666 708.30 RSD
Consumed electricity 425.15 kWh × 14.15 6,015.87 RSD
Subtotal (before excise tax) Sum of items 1-4 9,506.89 RSD
Excise tax (7.5%) 9,506.89 RSD × 7.5% 713.02 RSD
TOTAL TO PAY Sum of all items 10,219.91 RSD

Rate Information

Privileged Consumer Rate
0.816
Distribution Access Rate
121.79
Distribution Active Rate
1.666
Excise Tax Rate
7.5%

Per-Meter Allocation for Tenant

Meter Meter Total (kWh) Tenant Allocation % Allocated to Tenant (kWh) Of Tenant Total
S-4.2
915.82 22.72% 208.07 48.94%
K-4.1
832.57 11.73% 97.66 22.97%
407
71.39 100.00% 71.39 16.79%
407-A
48.03 100.00% 48.03 11.30%
Total Allocated to Tenant 425.15 kWh = 100%

Note: Shown allocations reflect any custom period reduction, so their sum may differ from the bill's base meter allocations.

This bill was generated on April 03, 2026 p.m.30 15:29 by the Chinese Cultural Center Electricity Management System.