Tenant Information

Tenant Name: XINGJUN CONSTRUCTION
Office Number: 603
Area: 91.95 m²
Floor: 6

Bill Information

Calculated According to: Invoice 40030262
Issued By: ELEKTROPRIVREDA SRBIJE
Period: April 2025
Generated: Jul 22, 2025 13:04

Consumption & Rate Information

15.00
Granted Power (kW)
210.64
Total Spent (kWh)
13.88 RSD
kWh Price

Calculation Breakdown

Description Calculation Amount
Fee for stimulus of privileged consumers 210.64 kWh × 0.816 171.88 RSD
Access to the system for distribution of electricity/Granted power 15.00 kW × 108.51 1,627.65 RSD
Access to the system for distribution of electricity/Active 210.64 kWh × 1.433 301.85 RSD
Consumed electricity 210.64 kWh × 13.88 2,923.68 RSD
Subtotal (before excise tax) Sum of items 1-4 5,025.06 RSD
Excise tax (7.5%) 5,025.06 RSD × 7.5% 376.88 RSD
TOTAL TO PAY Sum of all items 5,401.94 RSD

Rate Information

Privileged Consumer Rate
0.816
Distribution Access Rate
108.51
Distribution Active Rate
1.433
Excise Tax Rate
7.5%

Per-Meter Allocation for Tenant

Meter Meter Total (kWh) Tenant Allocation % Allocated to Tenant (kWh) Of Tenant Total
S-4.3
350.73 18.75% 65.76 31.22%
K-6.1
152.55 4.59% 7.00 3.32%
P3/DBA-6F-3
0.00 100.00% 0.00 -
P3/DB-6F-3
2.29 100.00% 2.29 1.09%
Total Allocated to Tenant 75.05 kWh = 100%

Note: Shown allocations reflect any custom period reduction, so their sum may differ from the bill's base meter allocations.

This bill was generated on July 22, 2025 p.m.31 13:04 by the Chinese Cultural Center Electricity Management System.

For questions about this bill, please contact the property management office.