Tenant Information

Tenant Name: BINARY CONSULTING
Office Number: 409
Area: 47.03 m²
Floor: 4

Bill Information

Calculated According to: Invoice 39574232
Issued By: ELEKTROPRIVREDA SRBIJE
Period: February 2025
Generated: Jul 22, 2025 13:04

Consumption & Rate Information

15.00
Granted Power (kW)
336.19
Total Spent (kWh)
13.88 RSD
kWh Price

Calculation Breakdown

Description Calculation Amount
Fee for stimulus of privileged consumers 336.19 kWh × 0.816 274.33 RSD
Access to the system for distribution of electricity/Granted power 15.00 kW × 108.51 1,627.65 RSD
Access to the system for distribution of electricity/Active 336.19 kWh × 1.433 481.76 RSD
Consumed electricity 336.19 kWh × 13.88 4,666.32 RSD
Subtotal (before excise tax) Sum of items 1-4 7,050.06 RSD
Excise tax (7.5%) 7,050.06 RSD × 7.5% 528.75 RSD
TOTAL TO PAY Sum of all items 7,578.81 RSD

Rate Information

Privileged Consumer Rate
0.816
Distribution Access Rate
108.51
Distribution Active Rate
1.433
Excise Tax Rate
7.5%

Per-Meter Allocation for Tenant

Meter Meter Total (kWh) Tenant Allocation % Allocated to Tenant (kWh) Of Tenant Total
S-4.1
850.52 6.25% 53.16 15.81%
K-4.1
70.72 2.58% 1.82 0.54%
409
156.40 100.00% 156.40 46.52%
409-A
24.48 100.00% 24.48 7.28%
Total Allocated to Tenant 235.86 kWh = 100%

Note: Shown allocations reflect any custom period reduction, so their sum may differ from the bill's base meter allocations.