Tenant Information

Tenant Name: BARADINE INVEST
Office Number: 407-A
Area: 174.64 m²
Floor: 4

Bill Information

Calculated According to: Invoice 40030262
Issued By: ELEKTROPRIVREDA SRBIJE
Period: April 2025
Generated: Jul 22, 2025 13:04

Consumption & Rate Information

20.00
Granted Power (kW)
253.56
Total Spent (kWh)
13.88 RSD
kWh Price

Calculation Breakdown

Description Calculation Amount
Fee for stimulus of privileged consumers 253.56 kWh × 0.816 206.90 RSD
Access to the system for distribution of electricity/Granted power 20.00 kW × 108.51 2,170.20 RSD
Access to the system for distribution of electricity/Active 253.56 kWh × 1.433 363.35 RSD
Consumed electricity 253.56 kWh × 13.88 3,519.41 RSD
Subtotal (before excise tax) Sum of items 1-4 6,259.86 RSD
Excise tax (7.5%) 6,259.86 RSD × 7.5% 469.49 RSD
TOTAL TO PAY Sum of all items 6,729.35 RSD

Rate Information

Privileged Consumer Rate
0.816
Distribution Access Rate
108.51
Distribution Active Rate
1.433
Excise Tax Rate
7.5%

Per-Meter Allocation for Tenant

Meter Meter Total (kWh) Tenant Allocation % Allocated to Tenant (kWh) Of Tenant Total
S-4.2
32.66 19.04% 6.22 2.45%
K-4.1
126.50 9.59% 12.13 4.78%
P2/DBA-4F-2
26.34 100.00% 26.34 10.39%
P2/DB-4F-2
6.25 100.00% 6.25 2.46%
Total Allocated to Tenant 50.94 kWh = 100%

Note: Shown allocations reflect any custom period reduction, so their sum may differ from the bill's base meter allocations.

This bill was generated on July 22, 2025 p.m.31 13:04 by the Chinese Cultural Center Electricity Management System.